Not-So-Live Construction Cam

Hang on...The live cam will be up in a few days.


Sales or Information - 760-318-1110



Updated June 23rd, 2018


June 23rd update


We are rocking and rolling now. The steel framework is 90% completed on the east wall. It is looking massive. Just a few roof supports to be installed next week, then we move on to the north wall.

The north wall only has about 6 rows of block to go, then the steel will begin to be erected there. We now have 10 masons working on the wall, so progress should really speed up.

The west and south walls have an additional three rows of block as of today, but another 20 rows (at least) have yet to be installed, but since we have so many masons working now, it should go very quickly.

. The front landscaping area is being graded now, but util we get water, the plants will have to wait. Some of the hardscape will be installed while we wait for water. Overall, it will add to the feeling of nearing completion.

Next update in about a week.